Timeline Update No: 3 | 15th April 2021

We have put-up some special fencing which will reduce sound caused by the construction works.

The foundations have been completed and we have built up the walls which support the new floor. We have installed the new floor, which is made from concrete beams and blocks.

We are now starting to build-up the new walls, which include some steel called wind-posts to keep the walls straight.

New Building Update

Timeline Update No: 2 | 15th March 2021

We have been laying the foundations for the new classroom block.

The foundations have been dug and filled with steel reinforcement and concrete. The concrete was poured using a special pump to reach over the site.

We have installed a large underground tank where rainwater will be collected before slowly draining away.

We have also started work to make the school car-park larger.

Click below to download the Construction Site Safety Presentation and enter our poster competition.

Building H&S Presentation – John Grant School


Timeline Update No: 1 | 24th February 2021

Work has started to build our new Classrooms. In the last few weeks we have set-up the site security fencing and laid a rubble track so our machines can access the site. We have brought in our Site Manager’s office and some welfare cabins for our builders. We have started to level up the ground for the new building. Mrs Ashworth and Ms Ellis helped us to dig up the first pieces of grass to start the building project.